6b Newton Abbot - 25/00345/MAJ - Langford Bridge
PDF 2 MB
Additional documents:
Decision:
RESOLVED
RESERVED MATTERS BE GRANTED, subject to the following conditions and an additional INFORMATIVE which will advise that future developments related to the hereby approved road should be designed to minimise the reliance upon on street parking. The final wording to be agreed by the Head of Development Management in consultation with Councillors Bullivant and MacGregor.
1. Development in accordance with approved plans
|
1. Development in accordance with approved plans Date Received |
Drawing/Reference Number |
Description |
|
26 Feb 2025 |
WOLB2/3-1300 REV P1 |
Site Location Plan |
|
07 Apr 2025 |
ES23.051 PH4-02.03 REV P1 |
Primary Infrastructure Highway Sections |
|
19 Aug 2025 |
ES23.051 03.50 REV P1 |
Drainage Outfall Plan |
|
03 Nov 2025 |
ES23.051 SK-03.20 REV P3 |
Site-Wide Drainage Strategy - Catchment Areas |
|
03 Nov 2025 |
ES23.051 30.04 REV T1 |
Adoptable Highway Construction Details - Sheet 4 |
|
03 Nov 2025 |
ES23,051 REV A |
SuDS Maintenance Plan |
|
26 Nov 2025 |
PERSW24830-12B |
SUDs Proposals |
|
01 Dec 2025 |
ES23.051 PL-RMA-02.01 REV P3 |
Spine Road General Arrangement Plan |
|
01 Dec 2025 |
ES23.051 PL-RMA-03.00 REV P8 |
Drainage Strategy Sketch Overall Sheet |
|
01 Dec 2025 |
ES23.051 PL-RMA-03.01 REV P9 |
Drainage Strategy Sketch Inset Sheet |
|
01 Dec 2025 |
ES23.051 PL-RMA-10.02 REV P2 |
Spine Road Surfacing Plan Sheet 2 |
|
01 Dec 2025 |
ES23.051 PL-RMA-20.01 REV P2 |
Highway Visibility Plan Sheet 1 |
|
01 Dec 2025 |
ES23.051 PL-RMA-20.02 REV P2 |
Highway Visibility Plan Sheet 2 |
|
01 Dec 2025 |
ES23.051 PL-RMA-07.02 REV P3 |
Vehicle Tracking Plan - Refuse |
|
01 Dec 2025 |
ES23.051 PL-RMA-08.00 REV P3 |
Impermeable Area Plan |
|
01 Dec 2025 |
ES23.051 PL-RMA-09.00 REV P3 |
Overland Flow Flood Exceedance |
|
01 Dec 2025 |
ES23.051 PL-RMA-10.01 REV P3 |
Spine Road Surfacing Plan Sheet 1 |
|
01 Dec 2025 |
ES23.051 PL-RMA-07.01 REV P3 |
Vehicle Tracking Plan - Fire |
|
30 Jan 2026 |
PERSW24830-11B 2OF2 |
G.I. Proposals |
|
30 Jan 2026 |
PERSW24830-11B 1OF2 |
G.I. Proposals |
REASON: To ensure compliance with the approved drawings.
2. Landscaping implementation
Notwithstanding the hard and soft landscaping details shown on Green Infrastructure and SuDS proposals drawings numbered PERSW24830-11B 1of 2, PERSW24830-11B 2 of 2, and PERSW24830-12B, full details of the sizes, locations, specifications and maintenance strategy for the tree pits and rainwater garden annotated on PERSW24830-11B 2of2 shall be submitted to and approved in writing by the Local Planning Authority in consultation with the Lead Local Flood Authority and Devon County Council Highway Authority.
In all other respects, the approved hard and soft landscaping scheme shall be carried out strictly in accordance with the approved details submitted on the approved Green Infrastructure and SuDS proposals drawings numbered PERSW24830-11B 1of2, PERSW24830-11B 2of2, and PERSW24830-12B.
All approved hard and soft landscaping, including the SuDS and Green Infrastructure proposals, shall be completed and thereafter managed and maintained in accordance with a timetable of implementation previously approved in writing by the Local Planning Authority.
Thereafter, following substantial completion of the development hereby permitted, all soft landscape works shall be protected, managed and maintained in accordance with the approved details and to a standard in accordance with the relevant recommendations of British standard 4428 1989 Code of Practise for general landscape operations. ... view the full decision text for item 6b