Decision Maker: Planning Committee
Made at meeting: 26/11/2019 - Planning Committee
Decision published: 28/11/2019
Effective from: 26/11/2019
Decision:
Resolved
Permission be granted subject to the following conditions:
1. The development hereby permitted shall be begun before the expiry of three years from the date of this permission.
2. The works hereby permitted shall be carried out accordance with the application form and approved plans.
3. Implementation of landscaping scheme in first planting season following completion of development.
4. Lodges (within definition of caravan) to be occupied for holiday purposes only and not as a main residence. A register of occupiers to be maintained.
5. Limit to number of lodges (within definition of caravan) and engineering works to those identified.
6. No loudspeakers or amplified music shall be played or installed other than within the units hereby approved.
7. CEMP to include pollution control measures, tree protection, controls on lighting and responsibilities for delivery.
8. LEMP to include long term management of new and retained habitats
9. Submission of a travel plan to accord with the Transport Statement
10. Lighting on the lodges to be motion activated on a short timer (max. 3 minutes)
11. Only outdoor lighting approved by the LPA to be installed on the site
12. Submission of detailed design of permanent surface water drainage management system
13. Submission of detailed design of surface water drainage management system which will serve the development site for the full period of its construction
14. Submission of details of the exceedance pathways and overland flow routes across the site in the event of rainfall in excess of the design standard of the proposed surface water drainage management system
15. Submission of schedule of external materials
16. Any areas of decking shall be constructed of materials that are recessive in colour and shall be dismantled and removed from the site on or before the removal of the lodge/ caravan to which they are associated.
17. Provision of covered and lockable cycle parking for 10 cycles
18. Provision of an electric car charging point
19. Bollard lighting to be turned off at or before 1.30am
20. A code of occupation to be provided in all lodges which shall include the requirement that noise must be kept to a minimum after 10 pm.
(15 votes for, 0 against and 1 abstention)
Decision Maker: Planning Committee
Made at meeting: 26/11/2019 - Planning Committee
Decision published: 28/11/2019
Effective from: 26/11/2019
Decision:
Resolved
Permission be granted subject to the following conditions:
1. Time limit for implementation (3 years);
2. To be built in accordance with approved plans;
3. Garage to be constructed using pile and beam foundation, details of which shall be submitted and agreed before constructing the garage
(17 votes for and 0 against)
Decision Maker: Planning Committee
Made at meeting: 26/11/2019 - Planning Committee
Decision published: 28/11/2019
Effective from: 26/11/2019
Decision:
Resolved
Permission be refused for the following reasons:
1. The proposed development would constitute the provision of open market housing within the open countryside which is contrary to Policy S22. Whilst an element of affordable housing is proposed, the application is not accompanied by a viability assessment which evidences the requirement for the open market housing to cross subsidise the delivery of affordable homes on a rural exception site. The application is therefore contrary to Policies S21, S22 and WE5 of the Teignbridge Local Plan.
2. Insufficient information has been supplied to demonstrate that the proposal would not have a harmful impact on protected species contrary to policies EN8 (Biodiversity, Protection and Enhancement) and EN10 (European Wildlife Sites) of the Teignbridge Local Plan.
(11 votes for, 3 against and 2 abstentions)
Decision Maker: Planning Committee
Made at meeting: 26/11/2019 - Planning Committee
Decision published: 26/11/2019
Effective from: 26/11/2019
Decision:
Resolved
Consideration deferred pending a Member’s site inspection.
(13 votes for and 2 against)
Decision Maker: Planning Committee
Made at meeting: 26/11/2019 - Planning Committee
Decision published: 26/11/2019
Effective from: 26/11/2019
Decision:
Resolved
Permission be granted subject to the following conditions:
1. Standard time limit
2. Works in accordance with approved plans
3. Bat Mitigation Plan
(14 votes for, 0 against and 1 abstention)
Decision Maker: Planning Committee
Made at meeting: 26/11/2019 - Planning Committee
Decision published: 26/11/2019
Effective from: 26/11/2019
Decision:
Resolved
Permission be granted subject to the following conditions:
1. Standard 3 year time limit for commencement.
2. Development to be carried out in accordance with the approved plans and documents.
3. Submission of materials for approval including a sample panel of stone work to be constructed on site for approval.
4. Full drainage details to be submitted and agreed prior to the commencement of works on site.
5. Submission and approval of hard and soft landscape proposals.
6. Implementation of bat mitigation/enhancement measures.
7. Parking for each plot to be provided prior to occupation and retained thereafter.
8. Details of siting, design and finish/materials of all meter boxes and inspection chambers to be submitted and agreed.
9. Removal of Permitted Development Rights.
10. Details of all rooflights to be submitted and agreed.
11. Works shall proceed in accordance with the Construction Management Plan (CMP).
12. Works shall proceed in accordance with the Contaminated Land Report.
13. Prior to any works commencing other than those for the access and internal road an appropriate Slow Worm survey work shall be undertaken
14. Full details of Management Company responsible for on-site communal areas to be submitted.
15. Requirement to install appliances at least as efficient as detailed in carbon calculator.
16. Provisions for electric vehicles.
17. Provisions for bird boxes, if appropriate.
(12 votes for, 1 against and 3 abstention)
Decision Maker: Overview & Scrutiny Committee
Made at meeting: 12/11/2019 - Overview & Scrutiny Committee
Decision published: 20/11/2019
Effective from: 12/11/2019
Decision:
Consideration was given to the agenda report which provided an update on the consultation results on the draft policy. During Committee discussion concern was expressed that: there were a variety of vehicle plug-in designs and it was considered that Government policy should seek a standardised plug in system for electric vehicles; rural area would miss out on electric plug-in locations; and the resources involve in making and disposing of car batteries, and the charging of batteries.
The Portfolio Holder for Waste Management and Environmental Health advised that car manufacturers were pursuing the electric vehicle option for the future, and he understood research was looking into the reuse of second hand electric car batteries.
RECOMMENDED
The Executive be advised that the Committee recommends approval of the Electric Vehicles, Infrastructure and Ultra Low Emission Vehicle Policy.
Lead officer: David Eaton
Application made and fee paid. Premises
inspected and compliance assessed with legislation and statutory
guidance. 3 Star licence issued in accordance with risk rating
guidance.
Decision Maker: Environmental Protection Manager
Decision published: 15/11/2019
Effective from: 15/11/2019
Lead officer: David Eaton
Application made and fee paid. Premises
inspected and compliance assessed with legislation and statutory
guidance. 3 Star licence issued in accordance with risk rating
guidance.
Decision Maker: Environmental Protection Manager
Decision published: 15/11/2019
Effective from: 15/11/2019
Lead officer: David Eaton
Application made and fee paid. Premises
inspected and compliance assessed with legislation and statutory
guidance. 1 Star licence issued in accordance with risk rating
guidance.
Decision Maker: Environmental Protection Manager
Decision published: 15/11/2019
Effective from: 15/11/2019
Lead officer: David Eaton
Application made and fee paid. Premises
inspected and compliance assessed with legislation and statutory
guidance. 3 Star licence issued in accordance with risk rating
guidance.
Decision Maker: Environmental Protection Manager
Decision published: 15/11/2019
Effective from: 15/11/2019
Lead officer: David Eaton
Application made and fee paid. Premises
inspected and compliance assessed with legislation and statutory
guidance. 1 Star licence issued in accordance with risk rating
guidance.
Decision Maker: Environmental Protection Manager
Decision published: 14/11/2019
Effective from: 14/11/2019
Lead officer: David Eaton